  2. ENERGYINTEROP-281 367: Missing Interactions
  3. ENERGYINTEROP-273

General - Not able to map all the IRC interactions to the current spec

    XMLWordPrintable

    Details

    • Type: Sub-task
    • Status: Closed
    • Priority: Major
    • Resolution: Fixed
    • Affects Version/s: wd17
    • Fix Version/s: wd25
    • Component/s: spec
    • Labels:
      None
    • Resolution:
      Hide

      Make changes to services, including addition of resource enrollment/verficiation, and measurement as agreed in EL/WTC/BB meeting on February 18.

      Show
      Make changes to services, including addition of resource enrollment/verficiation, and measurement as agreed in EL/WTC/BB meeting on February 18.

      Description

      As of right now I am not able to map all the IRC requirements for interactions identified as needed for Demand Response in wholesale. here is what I was able to map so far:

      http://www.oasis-open.org/apps/org/workgroup/energyinterop/download.php/40404/Mapping_IRC-to-EITC_Interactions_20101124.docx

      I cannot determine right now if services and operations are missing or additional translation is needed.

        Attachments

          Activity

            People

            • Assignee:
              william.cox William Cox (Inactive)
              Reporter:
              edgardo.luzcando Edgardo Luzcando (Inactive)
            • Watchers:
              0 Start watching this issue

              Dates

              • Created:
                Updated:
                Resolved: