Uploaded image for project: 'OASIS Energy Interoperation TC'
  1. OASIS Energy Interoperation TC
  2. ENERGYINTEROP-303

lines 404-406: The description of the VTN and VEN roles don't match the accompanied figure (figure 3-2).

    XMLWordPrintable

    Details

    • Type: Improvement
    • Status: Closed
    • Priority: Minor
    • Resolution: Fixed
    • Affects Version/s: csd01 - Public Review Draft
    • Fix Version/s: wd19
    • Component/s: spec
    • Labels:
      None
    • Environment:

      : "Abdulla, Ghaleb M." <abdulla1@llnl.gov>

    • Proposal:
      Hide

      Accept recommendations

      Show
      Accept recommendations
    • Resolution:
      Hide

      Numbering comments suggest this is actually a reference to an earlier draft, perhaps wd17. Section has been re-written, drawings re-generated since then.

      Show
      Numbering comments suggest this is actually a reference to an earlier draft, perhaps wd17. Section has been re-written, drawings re-generated since then.

      Description

      The VTN is assigned to the promisee and the VEN is assigned to the promissor. I think the figure should be corrected since the statement in the paragraph makes sense to me.

      A minor comment: earlier the figures were referenced as figure 2 and 3, however, the figures are labeled as figure 2-2 and 2-3.

        Attachments

          Activity

            People

            • Assignee:
              toby.considine Toby Considine (Inactive)
              Reporter:
              toby.considine Toby Considine (Inactive)
            • Watchers:
              0 Start watching this issue

              Dates

              • Created:
                Updated:
                Resolved: