476 add "a" before "seller"
476 change "the" to "a:
477 change "on retailer" to "on a retailer"
501 add "is" before "called"
525 :insert space after "Table"
562 What does "transactioned resources" mean: just say "resource"
590 change "transactional" to "transactive"
519: change "transactional power" to "for transactive power" which is an amount of power delivered over an interval of time at a constant rate of delivery"
617 : change : "request for a single interval" to "request for power delivered over a single interval of time".
619 change "transactional" to "transactive" and "power"
649 change "replication" to "repetition"
651. delete "specific response rates"
652 change "transactive purchase of fixed blocks of energy" to "transactions of energy delivered at specified rates over an interval"
716: change "the customer" to "both customers and suppliers"
719: generally a VEN and not a VTN would participate in in DR program where the VTN is the controller.
719. Delete: "distributed energy program" unless it can be defined clearly.
739"load and usage projection: is nowhere defined or provided for.